Canada's National Laboratory for Particle and Nuclear Physics Laboratoire national canadien pour la recherche en physique nucléaire et en physique des particules

ARIEL - Group News

TItle Date Excerpt Attached Image

May 11 ARIEL Snapshot

11 May 2012

The e-Linac team participated in the ESSC review. Awarded contract for He buffer tank. VECC Test 2 systems under vacuum, bake over the weekend.

May 4 ARIEL Snapshot

04 May 2012

SRF cavity tuner mock-up assembled - spring characterization agrees with FEA analysis. ARIEL Device Requirement list issued for review. ARIEL building first large concrete raft slab pour completed.

April 27 ARIEL Snapshot

27 April 2012

Diagnostics boxes 2 and 4 equipped with diagnostics were installed in the VECC Test beam line. The DCCT Design Review was successfully conducted.

April 20 ARIEL Snapshot

20 April 2012

TRIUMF-VECC collabooration meeting in Kolkata. The e-gun solenoid was received. Draft tender for sub-atmospheric pumps submitted for review. Draft design notes covering the entire beamlines from e-gun to dump and targets completed and submitted for review..

April 13 ARIEL Snapshot

13 April 2012

E-gun beryllium copper anode finished in the machine shop. RFP for Quads sent out for review. High Power RF leader participating in KEK power coupler tests.

April 5 ARIEL Snapshot

05 April 2012

Phase I of the construction of the ARIEL building comes to an end. A mobile boom crane removed a large excavator from the 13-meter deep hole dug for ARIEL's foundation

March 30 ARIEL Snapshot

30 March 2012

The Safety Analysis Report for the Electron Hall and e-linac was submitted to CNSC in support of a construction licence March 26th.

March 23 ARIEL Snapshot

23 March 2012

ARIEL construction proceeds on all three fronts: ARIEL building, Electron Hall, Compressor building.

March 16 ARIEL Snapshot

16 March 2012

A very successful week with many tasks of long gestation coming to a finale: rapid progress in electron hall renovation; klystron HV power supply tender closed; 12.5 kV switchgear requisition prepared; e-gun ceramic waveguide requisition preparedCongratulations to all involved!

March 9 ARIEL Snapshot

09 March 2012

7-cell copper cavity delivered. KEK-TRIUMF ERL Technology Workshop took place Saturday, March 10 at TRIUMF.

Syndicate content