
| TItle | Date | Excerpt | Attached Image |
|---|---|---|---|
May 11 ARIEL Snapshot |
11 May 2012 |
The e-Linac team participated in the ESSC review. Awarded contract for He buffer tank. VECC Test 2 systems under vacuum, bake over the weekend. |
|
May 4 ARIEL Snapshot |
04 May 2012 |
SRF cavity tuner mock-up assembled - spring characterization agrees with FEA analysis. ARIEL Device Requirement list issued for review. ARIEL building first large concrete raft slab pour completed. |
|
April 27 ARIEL Snapshot |
27 April 2012 |
Diagnostics boxes 2 and 4 equipped with diagnostics were installed in the VECC Test beam line. The DCCT Design Review was successfully conducted. |
|
April 20 ARIEL Snapshot |
20 April 2012 |
TRIUMF-VECC collabooration meeting in Kolkata. The e-gun solenoid was received. Draft tender for sub-atmospheric pumps submitted for review. Draft design notes covering the entire beamlines from e-gun to dump and targets completed and submitted for review.. |
|
April 13 ARIEL Snapshot |
13 April 2012 |
E-gun beryllium copper anode finished in the machine shop. RFP for Quads sent out for review. High Power RF leader participating in KEK power coupler tests. |
|
April 5 ARIEL Snapshot |
05 April 2012 |
Phase I of the construction of the ARIEL building comes to an end. A mobile boom crane removed a large excavator from the 13-meter deep hole dug for ARIEL's foundation |
|
March 30 ARIEL Snapshot |
30 March 2012 |
The Safety Analysis Report for the Electron Hall and e-linac was submitted to CNSC in support of a construction licence March 26th. |
|
March 23 ARIEL Snapshot |
23 March 2012 |
ARIEL construction proceeds on all three fronts: ARIEL building, Electron Hall, Compressor building. |
|
March 16 ARIEL Snapshot |
16 March 2012 |
A very successful week with many tasks of long gestation coming to a finale: rapid progress in electron hall renovation; klystron HV power supply tender closed; 12.5 kV switchgear requisition prepared; e-gun ceramic waveguide requisition prepared. Congratulations to all involved! |
|
March 9 ARIEL Snapshot |
09 March 2012 |
7-cell copper cavity delivered. KEK-TRIUMF ERL Technology Workshop took place Saturday, March 10 at TRIUMF. |